Brocklesby Biogas

Project Details

The full scale of our work at Brocklesby Biogas has been all encompassing from the design, project management, instillation and commissioning of the site which includes the instillation of 5 Jenbacher CHP engines totalling 3.4MW, a 3MW CHP waste heat recovery system, a CHP waste heat steam boiler producing 700kg/hr of saturated steam, a 599kW standby biogas boiler and a 1,600m3/hr high temperature flare system.

Further to this we’ve also installed welfare, laboratory and office facilities, an on-site HV/LV network and off-site HV cable to the local substation – a distance of 6.8km.

Advantage Biogas will be responsible for the full operation and maintenance of the plant including the CHPs and the provision of an on-site TCM (Technically Competent Manager)